The following frequently asked questions could help you better prepare your Application for Service. If you require additional answers to your questions, please email businesscenter@wisconsinpublicservice.com or call 877-444-0888, 7 a.m. to 5 p.m. Monday - Friday (CST).

When should I apply for new service?
As soon as possible after you have the property purchased, your final site plan prepared, and your sub-contractors selected.

Back to top

What information is required to apply for new service?
  • The responsible party for the construction charges, along with their mailing address and phone number.
  • The General Contractor or the point of contact and their phone number
  • The service address of the new building location
  • The Final Approved site plan with the preferred location of the electric and gas meters marked, as well as the private underground facilities marked and paths located
  • The sub-contractor(s) name(s) and phone number(s), who can provide us with the building load information
  • The approximate date you will be ready for service.

Back to top

What is the cost for a new gas and electric service installation?
The costs are dependent on many factors. After we process your application for the new service with your site plan and building load, our designer will send you a letter and contract related to the costs. Some of these factors include:
  • Distances from the primary to your desired meter locations
  • Overhead or underground service desired
  • Size of the system needed to meet your building load
  • Winter construction charges
  • Permits and fees

Back to top

I have permission from the neighboring business to cross their property for service to my new building. Does WPS require something in writing?
Yes. You will need to provide us with a signed and notarized easement. When this legal document is recorded as a permanent record, we can schedule and install your new service.

Back to top

Will I need to submit an electrical inspection or certificate of compliance prior to WPS installing the new electrical service?
It is always best to check with your local municipality for their specific requirements.

Back to top

What information should I provide on my Property Site Sketch and Liability Waiver form?
The information needed for new service can be found on the Providing a Property Site Sketch page.

Back to top

During the winter months, are underground service installations possible?
Yes, we will install underground facilities all year long. However, there will be additional charges due to the increased costs associated with construction during the winter months. Additional "Winter Construction Charges" will be charged between December 1 and March 31, to help recover the additional costs associated with underground service installation during the winter months. (For Michigan customers, the effective dates are between November 15 and April 30).

Back to top